KIRYANDONGO DISTRICT LOCAL GOVERNMENT COMPLETED/ONGOING PROJECTS FOR THE FINANCIAL YEAR 2021/2022
KIRYANDONGO DISTRICT LOCAL GOVERNMENT COMPLETED/ONGOING PROJECTS FOR THE FINANCIAL YEAR 2021/2022
Project Name |
Contractor |
Contractor amount |
Source of funding |
Status |
PRODUCTION DEPARTMENT ACDP PROJECTS |
|
|
|
|
Construction of Storage facility, Two Stance Pit Latrine and Store Fence for KIGUMBA PRODUCE DEALERS ASSOCIATION |
Monaco Construction Limited |
223,881,627 (MAAIF 67% = 150,000,627 Farmer Org. 33% = 73,880,937) |
ACDP |
Completed awaits commissioning |
Construction of a Maize Storage Structure, Maize Milling Plant and a Two stance lined Latrine and Urinal Shower (2) for KIRYANDONGO DISTRICT EXTENSION WORKERS ASSOCIATION |
Ramucon Engineering Services Ltd |
331,668,750 (MAAIF 67% = 222,218,063
|
ACDP |
Construction of Structure Complete (Shuttering completed and painting not yet done)
Maize Mill not yet Installed.
(80% Completion Level) |
Construction of a Maize Storage Structure, Maize Milling Plant and a two stance pit latrine for MBOIRA UNITED COOPERATIVE SOCIETY |
Stone Memorial |
223,965,000 (MAAIF 67% = 150,056,550 Farmer Org% = 73,908,450) |
ACDP |
Construction of Structure Complete. (Pending works: Shuttering completed and painting not yet)
Maize Mill installation on going |
Construction of Maize Storage Structure, Maize Milling Plant and a two stance pit latrine for NYAMAHASA |
Lubra Contractors |
298,620,000 (MAAIF 67% = 200,075,400 Farmer Org 33% = 98,544,600) |
ACDP |
Construction of Structure Complete. (Pending works: Shuttering and painting)
Maize Mill not yet Installed. |
Construction of a Maize storage Structure, Maize Milling Plant and a two stance pit latrine for KYANKENDE |
Kambugu Contractors |
298,667,250 (MAAIF 67% = 200,107,058 Farmer Org 33% = 98,560,193) |
ACDP |
Construction of Storage structure at roofing level. |
Supply of Laboratory Equipment for Agricultural Laboratory |
Ssesom (U) Ltd |
39,695,000 |
Agric. Ext. Grant dev’t |
Completed and items delivered. |
Procurement of motorcycles to production department |
Mantra |
22,000,000 |
SDG (Production) |
Completed |
HEALTH DEPARTMENT |
|
|
|
|
Titling of land for 05 government institutions at the following areas:- Karuma HC II, Yabweng HC II, Diika HC II, Mutunda HC III and Tecwa HC II |
Force account |
31,000,000 |
SDG (Health) |
At deed plan level |
Fencing of Mutunda HC III |
Ssekago F construction LTD |
152,633,000 |
SDG (Health) |
Completed awaits commissioning. |
Renovation of Kigumba HC III |
Ssekago F construction LTD |
53,999,402/= |
SDG (Health) |
Completed awaits commissioning. |
EDUCATION DEPARTMENT |
|
|
|
|
Construction of a two-class room block at Nanda P/S |
Baguma & sons services limited |
62,801,736 |
SDG (Education) |
Completed awaits commissioning. |
Construction of a two-class room block at Kitwara P/S |
Baguma & sons services limited |
72,635,207 |
SDG (Education) |
Completed and commissioned |
Construction of a two-class room block at Ndabulye P/S |
Baguma & sons services limited |
62,801,736 |
SDG (Education) |
Completed awaits commissioning. |
Construction of a five stance VIP latrine at Kiryandongo BCS P/S |
Kamoga enterprises LTD |
23,536,750 |
SDG (Education) |
Construction works completed awaiting painting |
Construction of a five stance VIP latrine at Kyamugenyi COU P/S |
Lubra Contractors LTD |
23,536,750 |
SDG (Education) |
Completed and commissioned |
Construction of 2 five stances VIP latrines at Wakisanyi P/S ( Two sets of five stances VIP lined latrines) |
Muzira Goodies General Agencies |
47,073,500 |
SDG (Education) |
Completed and commissioned |
Provision of the furniture ( 40 Three seater desks) to Nanda P/S each desk at Shs. 189,000 |
Cindy General Contractors LTD |
7,560,000 |
SDG (Education) |
Delivered |
Provision of the furniture ( 46 Three seater desks) to Dyang P/S each desk at Shs. 189,000 |
Cindy General Contractors LTD |
8,694,000 |
SDG (Education) |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Kitwara P/S each desk at Shs. 189,000 |
Cindy General Contractors LTD |
7,560,000 |
SDG (Education) |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Kizibu COU P/S |
Kamoga Agency |
7,600,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Mpumwe P/S |
Kamoga Agency |
7,600,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Katamarwa P/S |
Kamoga Agency |
7,600,000 |
SDG |
Delivered |
Provision of the furniture ( 41 Three seater desks) to Kiryandongo COU P/S |
JB Bbosa |
7,779,000 |
SDG |
Delivered |
Provision of the furniture ( 80 Three seater desks) to Okwece P/S |
JB Bbosa |
15,120,000 |
SDG |
Delivered |
Provision of the furniture ( 31 Three seater desks) to Diika P/S |
JB Bbosa |
5,859,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Katulikire P/S |
JB Bbosa |
7,560,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Gwara P/S |
JB Bbosa |
7,560,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Kitongonzi P/S |
JB Bbosa |
7,560,000 |
SDG |
Delivered |
Provision of the furniture ( 40 Three seater desks) to Kyembera P/S |
Kamoga Agency |
7,600,000 |
SDG |
Delivered |
Completion of the construction of Kitwara seed secondary school |
CMD Enterprises LTD |
100,633,000 |
U-GIFT |
Completed awaits commissioning |
Construction of Kigumba Town Seed S.S |
CMD Investments LTD |
748,502,000 as per the budgeted figure |
U-GIFT |
No objection has been received and file being submitted to solicitor General for approval and then CC for the district to award later |
Restoration of schools both 76 primary schools and 07 secondary gov’t aided |
Various contractors |
499,000,000 |
Capital grant to schools |
Completed awaits commissioning |
Construction of a two classroom block at Kihura P/S |
Lubra contractors LTD |
69,568,225 |
SDG( Education)- Supplementary budget |
Completed and commissioned |
Construction of two sets of 5 stances lined VIP latrines at Kyembera and Comboni Parents P/S |
ARID Enterprises |
48,000,000 |
SDG( Education)- supplementary budget |
Completed and commissioned |
ROADS AND ENGINEERING |
|
|
|
|
Mechanized maintenance of Kirwala – Kisorosoro - Diika road 13 Km |
Force account |
55,430,000 |
URF |
Completed awaiting commissioning |
Mechanized maintenance of Rwakayata - Katamarwa road 6 Km |
Force account |
42,962,000 |
URF |
Completed awaiting commissioning |
Mechanized maintenance of Masindi Port - Kimengo Road, 8 Km |
Force account |
29,000,000 |
URF |
Completed awaiting commissioning |
Mechanized maintenance of Laboke-Kololo road 12.5 KM |
Force account |
80,374,000 |
DDEG |
Completed awaiting commissioning |
WATER |
|
|
|
|
Deep borehole drilling at Nyamuntende in Kiryandongo S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Kamusenene in Kiryandongo S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Kooki in Kiryandongo S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Tugo in Kiryandongo S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Katuugo in Masindi Port S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Kiryanseka in Masindi Port S/C |
ROK Technical Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Alero A in Mutunda S/C |
LHM Ground Water Exploration and Geo Mapping Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Kasanja B in Mutunda S/C |
LHM Ground Water Exploration and Geo Mapping Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Kisura East in Mutunda S/C |
LHM Ground Water Exploration and Geo Mapping Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Nyakibete I in Kigumba S/C |
LHM Ground Water Exploration and Geo Mapping Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Deep borehole drilling at Nkwenda II in Mboira S/C |
LHM Ground Water Exploration and Geo Mapping Services Ltd & KLR-Uganda Ltd. |
32,312,000 |
DWSCG |
Completed and commissioned |
Borehole Rehabilitation at Sambya Kiryandongo S/county |
Kahora Technical Services Ltd. |
10,632,000 |
DWSCG |
Completed and commissioned |
Borehole Rehabilitation at Nyamahasa P/School- Nyamahasa S/C |
Kahora Technical Services Ltd. |
11,532,000 |
DWSCG |
Completed and commissioned |
Borehole Rehabilitation at Mutunda P/School - Mutunda S/C |
Kahora Technical Services Ltd. |
12,232,000 |
DWSCG |
Completed and commissioned |
Borehole Rehabilitation at Kaduku Hill Masindi Port S/C |
Kahora Technical Services Ltd. |
12,582,000 |
DWSCG |
Completed and commissioned |
Borehole Rehabilitation at Jeeja I Kigumba S/C |
Kahora Technical Services Ltd. |
10,632,0000 |
DWSCG |
Completed and commissioned |
Siting and drilling of a Production Well at Nyawino RGC Kiryandongo S/C |
ROK Technical Services Ltd |
40,000,000 |
DWSCG |
Completed and commissioned |
Feasibility study and design of a solar-powered mini-piped water supply system at Nanda RGC Mutunda S/C |
Aquatech Enterprises (U) Ltd. |
52,000,000 |
DWSCG |
Completed and commissioned |
NATURAL RESOURCES MANAGEMENT/USMID-AF PROJECTS |
|
|
|
|
Construction of Nyamusasa playfield |
S & M Civil Engineering and General Supplies LTD |
1,413,558,000 |
USMID-AF |
Awarded |
Full rehabilitation of Nanda -Popara Road. |
Universal Engineering (U) LTD |
500,000,000 |
USMID-AF |
Awarded |
Titling of land for 12 government institutions at the following areas:- District Hospital, hospital lagoon, the land where the DSC and agricultural laboratory is situated, Karungu II P/S, Kisekura P/S, Mutunda Sec. school, Kigumba Sec School, Bweyale Public P/S, Mboira Sec School, Kaduku HC II and Nyama P/S |
Force account |
100,000,000 |
DDEG |
At deed plan level |
Raising of 45,000 assorted trees ( Musisizi, Pines, Eucalyptus) by the District Forestry Officer |
Force account |
6,557,000 |
DDEG |
Distribution done to the interested farmers for planting. |
Trade, Industry and Local Development- DRDIP projects |
|
|
|
|
Construction of 2 three in one classroom block,3 blocks of 5 stances drainable latrine, and installation of two 10,000litres capacity stainless at Masindi port Primary School |
First drop water solution enterprises ltd |
449,017,269
|
DRDIP |
Completed only waiting for commissioning
|
Construction of 2 three in one classroom block,3 blocks of 5 stances drainable latrine, installation of two 10,000litres capacity stainless at Kigumba Muslim Primary school |
Ssekago f. Construction company ltd
|
446,845,485
|
DRDIP |
Completed only waiting for commissioning
|
Construction of 2 three in one classroom block,3 blocks of 5 stances drainable latrine, and installation of two 10,000litres capacity stainless at Kibanda SS Secondary school.
|
Monaco contractors ltd
|
456,588,245
|
DRDIP |
Completed only waiting for commissioning
|
Construction of 2 Blocks of 2-Units Staff houses, Kitchens and Pit latrines Kawiti primary school.
|
Sessom ltd
|
429,666,354
|
DRDIP |
Completed only waiting for commissioning
|
Construction of Maternity ward, Placenta pit,4 stance drainable latrine, supply and delivery tanks of 10,000lts stainless steel at Panyadoli H/C II |
Lubra contractors ltd
|
640,172,398
|
DRDIP |
Completed only waiting for commissioning
|
Completion of Admiration Block |
Solution d’infrastructure ltd
|
1,966,949,500 |
DRDIP |
Completed only waiting for commissioning
|
Construction of one Unit staff house, Kitchen and 2 stance drainable latrine at Panyadoli Health Center III
|
Monaco Contractors ltd |
353,212,523
|
DRDIP |
Roofing completed, plastering and fixing of doors and windows |
Full Rehabilitation of Katulikire-Panyadoli Road (10.6km)
|
Nipe Technical services ltd |
549,154,200 |
DRDIP |
Gravelling done working on drainage |
Full Rehabilitation of Reception Center-Magamaga FDP-Panyadoli H/C 111 Road.(3.8km) |
Tic Lokere Enterprises ltd |
331,995,531
|
DRDIP |
Completed awaiting commissioning |
Construction of Martenity ward, Incenirator and Medical waste pit at Panyadoli health Centre 111 |
Kambugu R. Contractors ltd |
660,562,278 |
DRDIP |
Roofing completed, fixing windows and doors |
Construction of 2 blocks of 3 classroom each,3 blocks of 5 stances drainable pit latrine, supply and installation of two 10,000litres capacity stainless, supply of 108 three seater desks, 6 tables and 6 chairs at Kifuruta Primary school in Kifuruta I- Apodorwa- Mboira Sub county |
Ssekago F Construction Ltd |
487,824,747 |
DRDIP |
Contract signed and mobilisation of materials to start work |
Construction of 2 blocks of 3 classroom each,3 blocks of 5 stances drainable pit latrine, supply and installation of two 10,000litres capacity stainless, supply of 108 three seater desks, 6 tables and 6 chairs at Opok Primary school in Opok I Chopelwor- Kicwabugingo sub county |
First drop enterprises Ltd |
480,566,436 |
DRDIP |
At solicitor general for approval |
Full rehabilitation of Kigumba-Kinyara-Masindi Port road ( 15.1Km) in Kiigya, Kinyara I and II- Kiigya-Kigumba/Masindi Port sub counties |
Tic Lokere enterprise |
892,292,100 |
DRDIP |
Bush clearing on going |
Full rehabilitation of Siriba-Kalwala-Kiryampungula (11.3 Km) in Kalawala, Kikube- Kiryandongo sub county |
Tic Lokere enterprise |
1,000,262,500 |
DRDIP |
Grading done mobilizing for dumping of marram |
Full rehabilitation and design and build of a box culvert at Siriba stream on Kiryandongo-Kitwara road ( 20 Km) in Kiryampungula, Kikube, Kiryandongo sub county |
|
2,048,531,625 |
DRDIP |
Evaluation done |
Construction of general/maternity ward, incinerator and 4 stance pit latrine with showers installation of solar power, supply and installation of 10,000 ltrs stainless steel tank and 3,000 ltrs PVC tank, supply of 15 beds and mattresses at Masindi Port HC III in Kimyoka, Waibango, Masindi Port Sub county |
Solution D’infrastructure Ltd |
704,310,285 |
DRDIP |
Contract signed and mobilizing materials |
Construction of general ward, and 4 stance pit latrine with showers, installation of solar power, supply and installation of 10,000 litres stainless steel tank and 3,000 litres PVC tank, supply of 17 beds and mattresses at Panyadoli HC III in Cluster K, Ranch I, Bweyale Town Council |
King star Construction ltd |
681,587,718 |
DRDIP |
At solicitor general for approval |
Construction of 1 block of doctors house, 1 stance drainable pit latrine with shower, supply and installation of 5,000 litres stainless steel tanks and 2,000 litres stainless steel tank with its stand at Panyadoli HC III in Cluster K, Ranch I, Bweyale Town Council. |
Monaco contractors Ltd |
362,786,555 |
DRDIP |
Contract signed and mobilizing materials |
Construction of 1 unit staff of 2 in one house, 1blocks of 2 stance drainable pit latrine with shower, supply and installation of 5,000 litres stainless steel tanks and 2,000 litres stainless steel tank with its stand at Panyadoli HC II in Panyadoli A, Kakwokwo, Mutunda Sub county |
Sesom U Ltd |
353,136,275 |
DRDIP |
Contract signed and mobilizing materials |
Full rehabilitation of Congodoki- Kiryandongo High school road ( 3.9 Km) in Cluster OQ, Ranch 37, Bweyale Town Council |
Angich enterprises |
353,470,257 |
DRDIP |
At solicitor general for approval |
Full rehabilitation of Magamaga- Gasper road ( 6.7 Km) in Cluster L and G, Ranch 37, Bweyale Town Council |
Teb Technical Services & contractors LTD |
521,776,500 |
DRDIP |
Grading done mobilizing for dumping of marram |
Key notes
- DDEG- Discretionary Development Equalization Grant
- SDG – Sector Development Grant
- URF- Uganda Road Fund
- DRDIP- Development Response Displacement Impact Programme
- ACDP- Agriculture Cluster Development Programme
- USMID_AF- Urban Municipal Infrastructural Development- Additional Funding